Friday, Jun 3, 2016
Work will result in intermittent periods when traffic will be detoured using alternate entrances and or exits
On Monday, May 16, 2016, the University will begin milling and repaving the roadway on the Campus Mall area on the Lawrenceville campus. The duration of the project will be from May 16 through June 8.
The project consists of new pavement, storm water drainage upgrades, widening the exit lane, installing conduit underground and re-striping. As a result of this work, there will be intermittent periods when traffic will be detoured using alternate entrances and or exits.
Thank you in advance for your cooperation during this important project. If you have any questions, please contact Facilities at ext. 5080.
Updates
Provided throughout the project to notify the campus community of changes in traffic patterns.
• On Monday, June 6, and Tuesday, June 7, from 7 a.m. to 5:30 p.m., the main entrance and exit to the Lawrenceville campus, along with the roadway that extends from Admissions to the Bart Luedeke Center, will be closed for paving. On Tuesday, the Annex lot will also be closed for line painting. For the remainder of the week through Thursday, the Campus Mall and joining roadways will be open with single lane closings for periods of time.
From 9 a.m. through the rest of the day, you will be unable to walk across the roadway from the commuter lot to the BLC. You will have to walk to the intersection at the corner of the BLC to cross over.
The South Entrance and exit will remain open for this period.
• On Thursday, June 2,, the Campus Mall entrance and exit, as well as the roadways that surround the Mall, will be closed. Drivers should use the South Entrance as an alternative.
• On Friday, May 27, and Tuesday, May 31, the main entrance will be closed in the morning and the main exit will be closed in the afternoon for milling and paving. Drivers should use the South Entrance as an alternative.
• On Thursday, May 26, the road around the mall and adjacent areas will be open for traffic beginning at 7 a.m. There will be one lane only open around the mall road.
• On Wednesday, May 25, the main exit will be closed from 7:30 a.m. through 7 a.m. on Thursday, May 26. The road along the Student Recreation Center, Alumni Gym, Daly's and Annex will also be closed during this time. The mall entrance, as well as the road that extends from the Bart Luedeke Center, Admissions and Moore Library towards North Hall, will remain open. The south entrance/exit will be open to exit the campus.
• On Tuesday, May 24, the main entrance to the Lawrenceville campus will be closed and no cars will be allowed to enter campus except through the south entrance from 7:30 a.m. to 5:30 p.m. The roadway that extends from the Bart Luedeke Center, Admissions and Moore Library towards North Hall will remain open.
• On Friday, May 20, work will take place on the roadway encircling the Campus Mall. There will be a minimum of one lane available at all times for traffic to move through the roadways and joining areas. Please go slow and use caution. There will be cones and directional signs in place during this process to guide drivers.
• On Thursday, May 19, the entrance side of the Campus Mall circle will have one lane blocked throughout the day. Vehicles will still be able to get through and access the areas as usual from the circle. Cones and directional signs will be placed to help guide drivers.